Hardscape

Concrete Calculator

Get cubic yards and exact bag counts for slabs, footings, cylindrical piers, and stairs, plus whether mixing bags or ordering ready-mix makes sense at your volume.

Updated

What are you pouring?

Dimensions

4 in for patios and walkways, 5–6 in where vehicles park.

%

10% is standard. Subgrade is never perfectly flat, and running short mid-pour creates a permanent cold joint.

Concrete needed

1.63cubic yards1.25 m³

44 cu ft (1.25 m³), including 10% overage

80 lb (36.3 kg) bags

74

60 lb (27.2 kg) bags

98

Ready-mix order

1.75cu yd

1.34 m³

Bag options

40 lb (18.1 kg) bag

Bags needed147
Approx cost$735

50 lb (22.7 kg) bag

Bags needed118
Approx cost$708

60 lb (27.2 kg) bag

Bags needed98
Approx cost$637

80 lb (36.3 kg) bag

Bags needed74
Approx cost$555

Ready-mix delivered

Bags needed1.75 cu yd (1.34 m³)
Approx cost$245–$385

Under 3 cubic yards most ready-mix suppliers add a short-load fee, often $100 or more. Worth pricing against bags at this size.

Call 811 (or your local utility locate service) before digging footings or post holes. It is free, and required in most of the US.

Standard bag yields

Yields are consistent across brands: a 40 lb bag yields 0.30 cu ft, 50 lb yields 0.375, 60 lb yields 0.45, and 80 lb yields 0.60. That makes 45 eighty-pound bags per cubic yard.

Weight figures use 150 lb per cubic foot, the standard density for normal-weight concrete.

How this is calculated

Volume, then bags

Concrete volume is length × width × thickness, all in feet, then divided by 27 for cubic yards. The thickness is the part people convert wrong, a 4 inch slab is 0.333 ft, not 4.

Bag yields are printed on the bag and are consistent across brands: a 60 lb bag yields 0.45 cubic feet, and an 80 lb bag yields 0.60. Divide your volume in cubic feet by the yield to get the count.

cubic yards = (length ft × width ft × thickness in ÷ 12) ÷ 27

Bag yields and coverage
BagYieldBags per cu ydBags per 4 in slab sq ft
40 lb0.30 cu ft900.11
50 lb0.375 cu ft720.09
60 lb0.45 cu ft600.074
80 lb0.60 cu ft450.056

Bags or ready-mix?

The crossover is around one cubic yard. Below that, bags are simpler and cheaper once you account for short-load fees. Above two yards, bags become genuinely impractical, a single cubic yard is 45 eighty-pound bags, which is 3,600 lb to carry and mix.

Ready-mix suppliers typically charge a short-load fee below about 3 yards, which can add $100 or more. There is also a hard constraint bags do not have: a large slab must be placed in one continuous pour, and a mixer cannot keep up with a truck.

Always order over

Add 10% to any concrete order. Subgrade is never perfectly flat, forms bow slightly under load, and the difference between a 3.9 inch and 4.1 inch average slab is real volume.

Running short mid-pour is the one failure you cannot fix. The first batch starts curing while you mix more, and you end up with a cold joint, a permanent plane of weakness through the slab.

Worked example

A 4-inch shed slab

A 10 ft × 12 ft slab poured 4 inches thick, with a 10% overage allowance.

Volume
10 × 12 × (4 ÷ 12) = 40 cu ft
With 10% waste
44 cu ft
Cubic yards
44 ÷ 27 = 1.63 cu yd
80 lb bags
44 ÷ 0.60 = 74 bags
Weight in bags
74 × 80 = 5,920 lb

1.75 yards of ready-mix, or 74 eighty-pound bags. At nearly three tons of bags, ready-mix wins here even carrying a short-load fee.